Firestone, CO
This Battery Energy Storage System (BESS) is projected to save United Power as much as $1 million annually by storing energy and releasing it during peak demand times.
The batteries supplied by Tesla will have a storage capacity of 16MW hrs — enough to simultaneously power 600 to 700 homes. These batteries are larger versions of the lithium ion batteries found in Tesla's electric vehicles.
Tesla, United Power, and ENGIE were partners in this project.
Parachute, CO
PS 1, 3, and 7 were three co-located project sites that ISI Solar engineered, procured, and constructed just outside of Parachute, CO.
Kearney, NE
The Kearney Solar Farm covers 54 acres with over 22,464 solar modules.
The system will generate 5.8 megawatts of renewable energy, which is about 5 percent of the city’s electrical demand.
The $11 million project is a partnership between the city of Kearney, Nebraska Public Power District, and Chicago-based SoCore Energy.
SoCore sells energy to Nebraska Public Power District, which in turn sells it to customers in the area. The University of Nebraska at Kearney has already contracted for half of the farm’s solar power.
Galesburg, IL
On this Illinois Solar Site, ISI Solar engineered, procured, and constructed this site. Partners on this project were Summit Ridge Energy and the utility Ameren.
Fitchburg, WI
Given the name “Tyto” and located in Fitchburg, WI, ISI Solar was responsible for the procurement and construction of this solar site. This Wisconsin project was a partnership with the developer, One Energy, and the local utility, Madison Gas and Electric (MG&E).